No.
|
Application case
|
Result:
|
|
1
|
Planning with Adherence to Schedule with Several Resources
-
Task with several task resources
-
The Planned duration of the task is preset.
-
Planning type = adher. to schedule
|
-
The planning is carried out by the scheduling along the duration of the task.
-
Scheduling does not prevent overload.
-
Overload will be indicated.
|
|
2
|
Planning with Adherence to Total Float with Several Resources
-
Task with several task resources
-
The Planned duration of the task is preset.
-
Planning type = adher. to total float
|
-
The planning is carried out by the scheduling along the duration of the task.
-
Scheduling does not prevent overload.
-
The float of overloaded resources is not used to compensate possible overload. If there is not sufficient float, resources will be overloaded
-
Resource 1 with overload: Float is used
-
Resource 2 with overload: Starts at the earliest start date.
|
|
3
|
Planning with adherence to capacity
-
Task with several task resources
-
The Planned duration of the task is preset.
-
Planning type = adherent to capacity
|
-
The task is planned by the scheduling without taking the Planned duration of the task into account.
-
Resources are not overloaded.
-
The float of the overloaded resource is used:
-
Resources are not scheduled during non-working days.
|
|
4
|
Resources with Vacation, Planning with Adherence to Schedule
|
-
Scheduling carries out the planning block-wise.
-
The resource is not planned by the scheduling during vacation.
-
On working days, the resource will possibly be planned with overload.
|
|
5
|
Resources with vacation > Task duration, Planning with adherence to schedule
|
-
The planning is scheduled before or at the start of vacation.
-
The effort is displayed as overload due to the unavailability of the resource on vacation.
-
If the entire task lies within the vacation period, it will be loaded at the calculated start date of the task.
|
|
6
|
Planning with Adherence to Total Float with Vacation
-
Vacation is entered for a resource.
-
Linear Load Profile
-
The duration of vacation is shorter than the task duration.
-
Planning type = adher. to total float
|
-
Outside the vacation period scheduling carries out the planning block-wise.
-
Available float is used. If the float is exhausted, scheduling will overload the resource.
-
This resource is not scheduled during vacation.
-
The planning is not splitted.
|
|
7
|
Planning with Adherence to Capacity with Vacation
-
Vacation is entered for a resource.
-
Linear Load Profile
-
The duration of vacation is shorter than the task duration.
-
Planning type = adherent to capacity
|
|
|
8
|
Planning with Adherence to Total Float with Requested end and
Fixing
= 0
-
Task with several task resources
-
The Planned duration is predefined.
-
Requested end on a task
-
Set the Fixing parameter = 0
-
The vacation of a resource is shorter than the task.
-
Planning type = adher. to total float
|
-
Scheduling plans the task on its Requested end.
-
When setting Fixing = 0, the Requested end is exceeded if necessary.
-
No consideration of float and possible overload since the specification of a Requested end causes loading with adherence to schedule.
-
The task is not moved.
|
|
8.1
|
Planning with Adherence to Total Float with Requested end and
Fixing
= 1
|
-
Scheduling plans the task on its Requested end.
-
When setting Fixing = 1, the Requested end is adhered to and the task is loaded with adherence to schedule.
-
Float and overloads are not taken into account.
-
The task is not moved.
|
|
8.2
|
Planning with adherence to Requested start on the resource assignment
Task with several task resources
|
|
|
9
|
Planning with adherence to capacity with Requested end and Fixing = 1
Task with several task resources
|
|
|
10
|
Planning with adherence to schedule of a task with predecessor, Requested start and Fixing = 0
-
Vacation is entered for a resource.
-
Linear Load Profile
-
The duration of vacation is shorter than the task duration.
-
Task with predecessor and Requested start, Fixing = 0
-
Planning type = adher. to schedule
|
-
The task does not start at the Requested start but after the predecessor has ended.
-
The vacation of the resource is taken into account.
-
Remaining duration= Planned duration
|
|
11
|
Planning with Adherence to Total Float with Effort > Availability
-
Task with several task resources
-
The Planned duration is predefined.
-
The capacity needed for the required duration exceeds the available capacity.
-
Planning type = adher. to total float
|
-
Scheduling exploits available float.
-
If no more float is available, the task is planned block-wise at the latest possible point in time.
|
|
12
|
Planning with Adherence to Capacity with Effort > Availability
-
Task with several task resources
-
The Planned duration of the task is predefined.
-
The capacity needed for the required duration exceeds the available capacity.
-
Planning type = adherent to capacity
|
-
Scheduling exploits available float. Scheduling is delayed until loading in is possible in a block. The project end date is possibly exceeded.
-
The resource is not planned during its vacation, the task is not splitted
|
|
13
|
Planning with Adherence to Total Float of a TA with Predecessor,
Requested end
and
Fixing
= 0
-
Vacation is entered for a resource.
-
Linear Load Profile
-
The duration of vacation is shorter than the task duration.
-
Task with predecessor and Requested start
-
Set the Fixing parameter = 0
-
Planning type = adher. to total float
|
-
The task does not start at the Requested start but after the predecessor has ended.
-
The vacation of the resource is taken into account.
-
Remaining duration = Planned duration
-
Float is not exploited since a task with date is always automatically loaded with adherence to schedule.
|
|
14
|
Planning with Adherence to Total Float of a TA with Predecessor, Requested end and Fixing = 0
-
Vacation is entered for a resource.
-
Linear Load Profile
-
The duration of vacation is shorter than the task duration.
-
Task with predecessor and Requested start
-
Set the Fixing parameter = 0
-
Planning type = adherent to capacity
|
-
The task does not start at the Requested start but after the predecessor has ended.
-
The vacation of the resource is taken into account.
-
Remaining duration = Planned duration
-
Float is not exploited since a task with date is always automatically loaded with adherence to schedule.
|
|
15
|
Calc. start for reporting of several task resources
|
-
Scheduling plans the resources with their remaining effort from the TAR Actual start on.
-
If the day following the Actual start date is a non-working day, the resource will be scheduled for the next working day.
-
The resource will possibly be overloaded.
|
|
16
|
Reporting on Vacation
|
-
Scheduling of resources without vacation is carried out in accordance with standard specifications.
-
The resource who has reported during vacation is scheduled for the first working day following the reporting period.
-
The resource will possibly be overloaded.
|