Customizer → Migration → Migration Packets panel → Completed Packets
Information
-
This module contains all completed migration packets.
-
Completed migration packets have either run successfully or were marked as completed manually.
-
Migration packets that were marked as completed manually cannot only be displayed as Completed with a green traffic light, but also as New, Failed, or Not relevant.
Legend
-
signalizes that this migration packet has not yet been executed.
-
signalizes that the migration packet has run successfully.
-
signalizes that this migration packet is still pending and waits for another migration packet to reach a certain status before it can be executed.
-
signalizes that this migration packet is not relevant for the current update type due to version dependencies.
-
signalizes that the migration packet has failed. There may be several causes for a packet to fail:
-
Many migration packages check whether the customizing on which the fix is based has changed before they are executed.
-
If this is the case, the change to the package is not made and the package is deemed to have failed.
-
In such a case, you have to check in the customizing whether and how the respective change can be made.
-
If the change has been made or if the change is not necessary, the package can be manually set to completed by activating the Completed checkbox.
-
This will move it from the Failed/pending packets area to the Completed Packets module.
-
-
-