Check Summarized Availability MOD007055

Access

Information

  • The current module and the Check Resource Structure module are used for availability check.

  • In some cases, a department resource may have incorrect availabilities. E.g.:

    • a departmental resource has a summarized availability even though the child resources have no availability at all.

    • a departmental resource has a negative summarized availability.

  • They can only be removed by deleting and reentering start and end periods of the child resource and of the department resource.

  • Stop

    • If you delete start and end periods, already entered vacation and absence days will be deleted as well.

    • Start and end periods must never be deleted separately.

Avoid the occurrence of incorrect availability