Project and Portfolio Management
Version 26 39.5.25 39.5.23 39.5.22 39.5.21 39.5.20 39.5.19 39.5.18 39.5.17 German English
Version 26 39.5.25 39.5.23 39.5.22 39.5.21 39.5.20 39.5.19 39.5.18 39.5.17 German English

Utilization of MOD009DA4

Access

Note

Information

  • In this module a simulation of the utilization of the selected resource will be displayed.

  • In this utilization, the value which has been entered and saved in the My Resource Requests for the respective resource in the Approved field will be considered as well.

    • If the value is changed and you save again, the display will be refreshed accordingly.

  • Project manager and department manager are thus provided with an option to simulate the impact of requests and approvals upfront.

Details

Note

  • No capacity adjustment will be carried out. Overloads and other impact which may be caused by requests and approvals will not be indicated.

See also : Information on Resource Requests/Approvals