Access
-
Program panel → Further... → Milestone Overview
Information
-
The module provides an overview of all master milestones and milestones of the selected program and its projects.
-
You also have the option to define one of the program master milestones displayed here as a main milestone.
-
Main milestones are used as reference points for the interval calculation of the master milestones to the other master milestones.
-
Details
-
Summary tasks (phases), milestones, and master milestones are displayed graphically as a bar chart and master milestones are additionally displayed as gates on a horizontal axis directly below the time scale.
-
On each master milestone symbol, the WBS code of the master milestone and the time interval to the main milestone date are specified (in weeks).
-
The calculated duration (Calc. start to Calc. end)
-
of the program is visualized by a dotted frame
-
of projects is visualized by a bar in the color of the project code.
-
Legend Program
|
Symbol |
Meaning |
Color |
Comment |
|---|---|---|---|
|
|
Calculated dates of the programs |
Calc. start and Calc. end are calculated by clicking on the Calculated schedule menu item button. |
|
|
|
Gate without delay Gate with delay Main gate/main milestone |
A gate is a master milestone of the planning objects.
|
|
|
Calculated dates |
The color of the bar is determined by the code of the planning object.
Code B Code C
Code E |
Calc. start and Calc. end are calculated by clicking on the Calculated schedule menu item button.
|
|
|
Master Milestones |
without delay
|
Tasks are defined as master milestones in the Schedule module. |
|
|
Master milestone delay |
Master milestone delay exists if Calc. end of a master milestone is later than its Latest end. |
|
|
Master Milestones |
without delay with delay |
Tasks are defined as master milestones in the Schedule module. |
|
|
Calculated dates of the summary tasks |
A summary task is a task in the structured schedule consisting of sub-tasks which are summarized here. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. |