Post Revenues MOD009DYU

Access

  • Project panel → Schedule → Post revenues/costs context menu command on a revenue resource in the required task

  • Project panel → Schedule → Click on the link on the ID of the required task → Task → Post revenues/costs context menu command on a revenue resource

Information

  • This module is a dialog module and therefore it has no independent function. It merely serves to record/post actual revenues for the selected task:

  • When opening the module, the corresponding project and task are automatically preselected.

Procedure

  • Use the Plus button to add a new record for recording revenue.

  • Record date and actual revenues in the Actual revenues field and possibly write a comment.

  • Save.