Project and Portfolio Management

Synchronizable Tasks MOD009DLV

Access

Information

  • This module is a dialog module and therefore it has no independent function. It is used to select tasks which are to be synchronized with PLANTA pulse or Jira.

  • When you open the module, the tasks of the project which have not yet been synchronized with PLANTA pulse or Jira are displayed.

    • No (master) milestones or summary tasks are displayed in the module since they cannot be synchronized.

Procedure

  • Activate the Relevant for external system checkbox for tasks which are to be synchronized.

    • As a result, only tasks which have not yet been synchronized will be displayed.

  • Click on Synchronize.