Access
-
Project (Proposal) panel → Further... → Milestone Overview
Information
-
This module provides an overview of all master milestones and milestones of the selected project and of its subprojects (if available).
-
It is possible to define one of the project (of the main project in the case of structured projects) master milestones displayed here as a main milestone.
-
Main milestones are used as reference points for the interval calculation of the master milestones to the other master milestones.
-
Details
-
Summary tasks (phases), milestones, and master milestones are displayed graphically as a bar chart and master milestones are additionally displayed as gates on a horizontal axis directly below the time scale.
-
On each master milestone symbol, the WBS code of the master milestone and the time interval to the main milestone date are specified (in weeks).
-
The calculated duration (Calc. start to Calc. end) of the projects will be visualized
-
by a dotted frame at main project project level
-
by a bar in the color of the project code at subproject level.
-
Note
-
If the module is opened from a subproject, the associated main project is displayed along with it.
Legend Project
|
Symbol |
Meaning |
Color |
Comment |
|---|---|---|---|
|
|
Calculated dates of the projects |
|
Calc. start and Calc. end of a project are calculated by clicking on the |
|
|
|
A gate is a master milestone of the planning objects.
|
Task
|
|
Master Milestones |
|
Tasks are defined as master milestones in the Schedule module. |
|
|
Calculated dates of the summary tasks |
|
A summary task is a task in the structured schedule consisting of sub-tasks which are summarized here. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. |