Resource Load per Month MOD009AG1
Access
- Multi-Project Management → Reports → Resource Overviews panel → Resource Utilization per Month
- Resource Management → Reports → Resource Overviews panel → Resource Load per Month
Information
- In this module, load of resources per month is displayed.
- If you have selected a department resource, the loads of the corresponding person resources will be displayed.
- By expanding the tree structure on the projects, you can have individual tasks displayed.
- Remaining load of the selected resource will be displayed on all levels.
Module variants
With actual loads | By selecting this module variant, Actual load values will be displayed below the remaining load values in the time scale. |
Note
- Tasks for which the resource in question is planned and which already have an Actual end will be displayed grayed out.