Risk Trend Analysis MOD0099N3
Access
- Project panel → Info Board → Risk Trend Analysis link in the Risk Trend area → Risk Trend Analysis
- Project (Proposal) panel → Risks/Opportunities → Risk Trend Analysis link in the Risks area → Risk Trend Analysis
- Project (Proposal, Program) panel → Further... → Risk Trend Analysis link (will be displayed if at least one status report exists)
Information
- In the Risk Trend Analysis module,
- the trend of the monetary damage resulting from the project risks is displayed graphically based on the project status reports.
- both current damage data and data from the status reports is displayed in table form and can be compared.
- Here, only status reports are displayed and analyzed which contain risk data and for which the Cost Trend Analysis checkbox is activated in the Configure Trend Analysis module.
Details
- The graphics contain three graphs: one each for possible, probable, and actual damage.
- Every profile has its own color. The meaning of each color is explained in the legend below the graphic.
- In tabular view, the reports are displayed below the active baseline sorted by report date in descending order.
Note on structured projects
- If it is a structured project, the risk trend analysis will only be displayed for the project level on which you currently are, i.e. either the risk trend analysis of the main project or that of the respective subproject.