Skip to main content
Skip table of contents

Status Report MOD009A52

Access

  • Project (Proposal) panel → Status → Click on the link in the ID field of the required status report → Status report (the already existing status report will be opened)
  • Project (Proposal) panel → Status → Click on the Create baseline or Create status report or Create final report button → Status Report (a new status report will be created)

Information

  • In this module, the data which was which was transferred from the Status module and frozen at a specific time is displayed. Here you cannot create or edit data. All fields are set to "Output".

Details

  • In the status report, the fixed data is split in several areas depending on the Costs, Effort, Dates, etc. factors.
  • In each area, the following data is displayed in the header:
    • Manager’s estimate on the respective factor
      • The estimate is visualized by a thumb symbol.
        • For factors for which no estimate has been entered yet, no thumb symbol is displayed here.
    • Comments
  • In the Costs, Effort, and Dates subareas, the following data will be displayed in addition:
    • Calculated frozen status of the deviation values of the respective factor: Total vs. Budget for costs and effort and Requested vs. Calculated for dates.
      • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
        • red: costs/effort overrun by more than 5%, delay of more than 5 days
        • yellow: costs/effort overrun by more than 5%, delay of up to 5 days
        • green: costs/effort not overrun, no delay
      • For dates, both the project end date deviation value as well as the master milestone end date deviation value are indeed instanced, the respective traffic light, however, refers to the worst of both values.
    • Project trend compared to the report that was active at the time of creation of the current report.
      • This is visualized by trend arrows with a specification of the percentage deviation of costs and effort and date deviation in days.
        • Arrow up = negative trend, arrow down = positive trend.
  • In some areas, details can be viewed by expanding the tree structure.
    • When you expand the
      • Costs area, details on the cost budget, two cost trend graphics as well as the Earned Value Analysis are displayed.
        • Graphic 1: cumulated total costs from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Graphic 2: total costs per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
      • Effort area, details on the effort budget and two effort trend graphics are displayed.
        • Graphic 1: cumulated total effort from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Graphic 2: total effort per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
      • Dates area, the dates and the duration of the project, milestone and master milestone dates, as well as milestone/master milestone trend graphics are displayed.
      • Risks/opportunities area,
        • the damage and gross profit values of the project resulting from risks or opportunities are displayed and
        • risks and opportunities are listed in the respective Risks and Opportunities subareas including their measures.

Notes and technical details

  • By default, only the values summarized via the project structure are displayed in the Status Report module, i.e., for each selected project the sum of the values of the project itself and of all of its subprojects (if there are any) are displayed.

Module Variants

BaseThe frozen status of project costs, effort, dates, quality as well as risks/opportunities will be displayed.
CompleteThe frozen status of the descriptive data, evaluation data, todo items, risks/opportunities, and process steps is displayed.

Release Status Report

Procedure

  • Click on the Release button.
  • Confirm the Status report cannot be changed after it has been released. dialog message Proceed? message with Yes.

Notes

Update Status Report

Information

  • If changes are made to the project between report creation and release that are to be included in the report, the status report must be updated before the release.

Procedure

  • Click on the Update button.
  • Confirm the Do you really want to update this data? dialog message with Yes.
    • As a result, dates, costs, and budgets of the project concerned are calculated anew (). This data and other possibly updated data will then be applied to the status report.
    • If comments, measures, and decisions have been changed in the Status module in the meantime, the new data will be included in the status report as well when it is updated.

Delete Status Report

Procedure

  • Click on the Delete button.
  • Confirm the Do you really want to delete this data? message with Yes.
  • The status report will be deleted.

Notes

Export Status Report to PowerPoint

Information

  • Via the PowerPoint symbol in the header area of the module, the data displayed in the module can be exported to a PowerPoint file. The PowerPoint template file must therefore be stored in the client.
    • In the PLANTA standard delivery, a standard !PowerPoint template is already contained in the client and can be adjusted individually if desired. For further information, see the PowerPoint Export topic in the PLANTA customizer help area.
JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.