Information
-
In PLANTA project, tasks can either be created individually or be copied as complete plans from other projects or project templates.
Where can I create tasks?
In the Schedule module of the required project
Open the project by
-
clicking
the search icon in the header area of the user menu or by opening a dialog box via CTRL+G and entering the ID of the required project or
-
by clicking on the link on the ID of the required project in any module.
Create Tasks Individually
Procedure
-
When initially opening the Schedule module, the following query is displayed: Adopt a schedule?
-
Answer the query with No.
-
Insert an empty task row, e.g., by clicking the New Task button in the action bar.
-
Enter a task name in the Task name field.
-
Save and click on the
Generate WBS code button below the project bar. As a result, an ID will automatically be generated for the new task in the Task field. In PLANTA standard, the breakdown structure codes are used as task IDs in schedules. This structure can be adjusted system-wide if necessary. For more information on this subject, see the "Structure Tasks" topic.
-
-
Create further tasks in the same way.
Copy Schedule
Procedure
-
When you open the Schedule module, the following confirmation prompt is displayed: Adopt a schedule?
-
Confirm the message with Yes.
-
-
The Copy Schedule module is opened at the bottom of the panel.
-
Select the project the schedule of which is to be copied from the listbox.
-
Start the copy operation by clicking on the Copy schedule button.
-
The schedule which was copied to the project is displayed and can be edited.
-
If you accidentally answered “No” to the prompt, you can reopen the Copy Schedule module by clicking the
Create a Schedule Using AI
-
The AI creates a schedule based on project information, a defined system prompt, the own prompt, and corresponding profit values.
-
The proposal can be applied, generated again, or discarded. After the generation, further adjustments are possible.
-
The creation happens in the Schedule module via a dialog message with the Create with AI button. Detailed information can be found in the module description.
- Links
- Anordnungsbeziehungen
- Links
- Anordnungsbeziehungen
- Anordnungsbeziehungen
- Links
- Structure Tasks / Work Breakdown Structure
- Vorgänge strukturieren / Projektstrukturplan
- Structure Tasks / Work Breakdown Structure
- Vorgänge strukturieren / Projektstrukturplan
- Structure Tasks / Work Breakdown Structure
- Vorgänge strukturieren / Projektstrukturplan
- Structure Tasks / Work Breakdown Structure
- Vorgänge strukturieren / Projektstrukturplan
- WBS MOD009ACB
- PSP MOD009ACB
- PSP MOD009ACB
- PSP MOD009ACB
- WBS MOD009ACB
- WBS MOD009ACB
- PSP MOD009ACB
- WBS MOD009ACB
- Schedule (Project) MOD0099AN
- Terminplan (Projekt) MOD0099AN
- Projektplan erstellen
- Create Project Plan
- Create Project Plan
- Projektplan erstellen
- Projektplan erstellen
- Create Project Plan
- Projektplan erstellen
- Create Project Plan
- Ressourcen im Projekt einplanen
- Plan Resources in a Project
- Plan Resources in a Project
- Ressourcen im Projekt einplanen
- Plan Resources in a Project
- Ressourcen im Projekt einplanen
- Ressourcen im Projekt einplanen
- Plan Resources in a Project
- Abhängigkeiten
- Abhängigkeiten
- Abhängigkeiten
- Dependencies
- Dependencies
- Dependencies
- Abhängigkeiten
- Dependencies
- Terminplan (Projekt) MOD0099AN
- Schedule (Project) MOD0099AN
- Videos zur Anwendung von PLANTA project/portfolio
- Videos on How to Use PLANTA project/portfolio
- Videos on How to Use PLANTA project/portfolio
- Videos zur Anwendung von PLANTA project/portfolio
- Videos on How to Use PLANTA project/portfolio
- Videos zur Anwendung von PLANTA project/portfolio
- Videos on How to Use PLANTA project/portfolio
- Videos zur Anwendung von PLANTA project/portfolio
- Schedule (Project) MOD0099AN
- Terminplan (Projekt) MOD0099AN
- Anordnungsbeziehungen
- Links
- Schedule (Project) MOD0099AN
- Terminplan (Projekt) MOD0099AN
- Abhängigkeiten
- Anordnungsbeziehungen
- PSP MOD009ACB
- Projektplan erstellen
- Vorgänge strukturieren / Projektstrukturplan
- Ressourcen im Projekt einplanen
- Terminplan (Projekt) MOD0099AN
- Videos zur Anwendung von PLANTA project/portfolio
- Dependencies
- Links
- WBS MOD009ACB
- Create Project Plan
- Structure Tasks / Work Breakdown Structure
- Plan Resources in a Project
- Schedule (Project) MOD0099AN
- Videos on How to Use PLANTA project/portfolio
- PSP MOD009ACB
- Abhängigkeiten
- Anordnungsbeziehungen
- Projektplan erstellen
- Ressourcen im Projekt einplanen
- Vorgänge strukturieren / Projektstrukturplan
- Terminplan (Projekt) MOD0099AN
- Videos zur Anwendung von PLANTA project/portfolio
- WBS MOD009ACB
- Dependencies
- Links
- Create Project Plan
- Plan Resources in a Project
- Structure Tasks / Work Breakdown Structure
- Schedule (Project) MOD0099AN
- Videos on How to Use PLANTA project/portfolio
- Abhängigkeiten
- Anordnungsbeziehungen
- Projektplan erstellen
- PSP MOD009ACB
- Ressourcen im Projekt einplanen
- Vorgänge strukturieren / Projektstrukturplan
- Terminplan (Projekt) MOD0099AN
- Videos zur Anwendung von PLANTA project/portfolio
- Dependencies
- Links
- Create Project Plan
- WBS MOD009ACB
- Plan Resources in a Project
- Structure Tasks / Work Breakdown Structure
- Schedule (Project) MOD0099AN
- Videos on How to Use PLANTA project/portfolio
- Abhängigkeiten
- Anordnungsbeziehungen
- PSP MOD009ACB
- Projektplan erstellen
- Vorgänge strukturieren / Projektstrukturplan
- Ressourcen im Projekt einplanen
- Terminplan (Projekt) MOD0099AN
- Videos zur Anwendung von PLANTA project/portfolio
- Dependencies
- Links
- WBS MOD009ACB
- Create Project Plan
- Structure Tasks / Work Breakdown Structure
- Plan Resources in a Project
- Schedule (Project) MOD0099AN
- Videos on How to Use PLANTA project/portfolio
- Abhängigkeiten
- Projektplan erstellen
- Anordnungsbeziehungen
- Ressourcen im Projekt einplanen
- Vorgänge strukturieren / Projektstrukturplan
- Terminplan (Gantt) - Projekt MOD0099AN
- PSP MOD009ACB
- Videos zur Anwendung von PLANTA project/portfolio
- Dependencies
- Create Project Plan
- Links
- Plan Resources in a Project
- Structure Tasks / Work Breakdown Structure
- Schedule (Gantt) - Project MOD0099AN
- WBS MOD009ACB
- Videos on How to Use PLANTA project/portfolio
- Abhängigkeiten
- Projektplan erstellen
- Anordnungsbeziehungen
- Vorgänge strukturieren / Projektstrukturplan
- Ressourcen im Projekt einplanen
- Terminplan (Gantt) - Projekt MOD009E1T
- PSP MOD009E1U
- Videos zur Anwendung von PLANTA project/portfolio
- Create Project Plan
- Dependencies
- Links
- Structure Tasks / Work Breakdown Structure
- Resource Planning in a Project
- Schedule (Gantt) - Project MOD009E1T
- WBS MOD009E1U
- Videos on How to Use PLANTA project/portfolio