Configure Trend Analysis MOD009BJL
Access
- Project panel → Info Board → Click on the button at the right-hand side of the project bar → Configure Trend Analysis
- Project panel → Status → Click on the Configure Trend Analysis button in the Status Report area → Configure Trend Analysis
- Program panel → Status → Click on the Configure Trend Analysis button in the Status Report area → Configure Trend Analysis
Information
- In this module you have the option to select the status reports which are to be used for different trend analyses (modules see under Details) or for a comparison of the planning states.
Procedure
- For status reports that you want to be
- taken into account in the cost, effort, risk, and opportunity analysis, activate the Cost trend analysis checkbox.
- taken into account in the milestone or master milestone trend analysis, activate the Milestone Trend Analysis checkbox.
- compared with the latest status in the Deviations module, activate the Milestone Trend Analysis checkbox.
Note
- If the selected project is a structured project, the checkboxes must be activated for the required report on all project levels (in the main project and in all subprojects).
Details
- Costs, effort, risk, and opportunity data can be found in the following modules:
- Cost Trend Analysis
- Effort Trend Analysis
- Risk Trend Analysis
- Opportunity Trend Analysis
- The respective graphical evaluations can also be found in the above mentioned modules as well as additionally in the Info Board, Cost Reports, and Effort Reports modules.
- Milestone or master milestone trend analysis data can be found
- in the Schedule module in the Milestone Trend and Master Milestone Trend module variants.
- The respective graphical evaluations can be found in the Info Board module.
See also: Status Report, Program Status Report |