Access
-
Project panel → Schedule → Click on the
button to open the Resource Requests module → Click on the
button on a request
-
Resource Management → Department Planning → Department Board panel → My Resource Requests → Click on the
on a request
-
Multi-Project Management → Project Planning → Multi-Project Board panel → Resource Request → Click on the
button on a request
Note
-
This module is only available if Resource requests/approvals are activated.
Information
-
In this module a simulation of the utilization of the selected resource will be displayed.
-
In this utilization, the value which has been entered and saved in the My Resource Requests for the respective resource in the Approved field will be considered as well.
-
If the value is changed and you save again, the display will be refreshed accordingly.
-
-
Project manager and department manager are thus provided with an option to simulate the impact of requests and approvals upfront.
Details
-
Which time grid will be used to represent utilization depends on the Resource requests: time grid parameter.
Note
-
No capacity adjustment will be carried out. Overloads and other impact which may be caused by requests and approvals will not be indicated.
|
See also : Information on Resource Requests/Approvals |