Progress MOD009ABC
Access
- Project panel → Further... → Progress
Information
- In this module,
- monitor the project progress,
- apply the forecast estimated by the reporters and
- define the functional degree of completion.
Details
- In the Completed field, the functional degree of completion can be entered.
- In the Forecast field at task level, there are summarized forecast values on remaining effort (for each task, sum of all resource assignments of the task). This field is preset with a traffic light function and is colored red or green depending on whether the Remaining effort is overrun or undercut by the forecast.
- When opening the task-resource-assignment, forecasts of individual resources on remaining effort which you have entered in the course of recording hours worked in the Time Recording module will also be visible in the Forecast field. The field is also preset with a traffic light.
- Forecast values can
- be entered manually. To do so, the Forecast field must also be cleared manually for future forecasts.
- or it must be copied to the Remaining effort field by clicking on the Copy forecast button. As a result, the Forecast field is automatically cleared for future forecasts. If no particular records are marked, all existing forecast values are copied automatically.
- In order for the adoption of forecasts to take effect you have to recalculate the schedule (by clicking on the calculation button in the toolbar).
- If Resource Planning with Requests/Approvals are used, the Adopt forecasts button is not available.
Note
- By clicking on the required task and selecting the Edit task context menu command you switch to the Task module. Here you can edit different paramaters and settings of the task.
Module Variants
Base | On the tasks, dates and effort are shown and at resource assignment level, only person and/or department resources, and only those for which no actual end date has been set yet, are displayed. |
With reverse postings | Like the base variant, but with additional display of possibly canceled hours and the respective revers postings at load level. Details on Reverse Postings |
Costs | On the tasks, dates and costs are shown, and at resource assignment level, only cost and revenue resources are displayed. |
With resources with and without actual end | At resource assignment level, both person and/or department resources with and without actual end date are displayed. |
Todo Items | Only tasks that have todo items (pending and completed ones) in the selected period are displayed. The todo items are displayed as well. The period is defined by the dates entered in the from and to fields. After clicking on the Apply changes button, the display will be refreshed. |
Actual Hours | Only tasks the resources of which have recorded working time in the selected period are displayed. The load records are displayed along with the recorded time. The period is defined by the date input in the from and to fields. After clicking on the Apply changes button, the display is refreshed. |