Skip to main content
Skip table of contents

Time Recording: Variant 2 (with Planned Hours Worked)

(Time Recording Below the Time Scale/ Comment / with Hours to be Worked)

Video Tutorial




Information

  • In the Time Recording module, the logged in employee can
    • record his/her hours worked
    • record and send forecasts of remaining effort
    • delete recorded hours worked (make reverse postings)

Details on sum area

  • In the top area of the module, two sum areas will be displayed
    • Hours to be Worked
      • For each day of the defined period, the number of planned hours worked is displayed below the time scale. Next to the heading, the summed up planned weekly value will be displayed in addition.
    • Worked
      • For each day of the week, the summed up number of recorded hours worked is displayed below the time scale. Next to the heading, the summed up actual weekly value is displayed.
      • An additional traffic light is implemented here which indicates on the basis of the recorded hours worked whether the planned hours worked are exceeded (red), undercut (yellow), or whether planned and actual values are equal (no highlighting).
        • If the hours to be worked function is activated, the hours to be worked values have not yet been defined for a resource, the traffic light for this resource is always red.

Details project area

  • The projects listed in the module are displayed in the following groups:
    • Time recording up to the end of the current week
      • Here, projects are displayed for which hours worked must only be recorded up to the last day of the current week.
    • Time recording also for future hours worked
      • Here, projects are displayed for which the recording of future hours worked is permitted, e.g. overhead projects.
    • My time recording favorites
      • Here, tasks are displayed with the respective projects which have previously been marked as favorites in one of the two groups mentioned above (Favorite star activated).
      • If tasks are listed in the My time recording favorites group, they are no longer displayed in the two groups mentioned above.
    • Non-postable objects (selected week)
      • In this group, tasks which have already been finished or locked or the projects of which have been set to "inactive" but have actual data in the selected week are displayed (with the respective projects). The display is required for the data to be traceable. For more information, see the entry under Caution.

Caution

  • In the module, only projects or tasks are displayed which
    • are not locked against the recording of hours worked
    • are not finished
    • are active
  • Tasks in which you have completed your work by activating the Completed checkbox will no longer be displayed in the module.
  • Exception: Non-postable objects (selected week) group See above.
  • If the project on which you want to record hours is not displayed in the module or if you cannot add the project (see the following chapter), please contact your project management administrator.

Details on views

  • In the Time Recording module you can switch between a weekly view and a daily view.
    • To do so, click on the
      or
      button at the upper left-hand side.
    • The weekly view is displayed by default.
    • In the daily view, today is displayed by default. If you go to another calendar week, Monday of the respective week will be displayed.

Record Own Hours Worked on Projects/Tasks in which One is Planned

Information

  • If no hours worked have been recorded yet, only projects in which the employee is planned directly are displayed initially in the Time Recording module. If hours worked have already been recorded on further projects/tasks (see the following chapter) these projects will also be displayed every time the Time Recording module is opened again.

Procedure

  • Extend the required project and task in the left window. There are empty load records for all days of the week by default.
  • Click below the required date in the line of the required weekday in the right window below the time scale.
  • Enter the required number of hours.
    • Immediately after entering the actual hours, the Remaining value will automatically be refreshed so that it is visible how many of the planned hours still remain.
  • Enter a comment on the left hand side in the record of the required day.
  • Save.
  • Enter hours and comments for all required days in the same way.

Scroll in the calendar

  • Via the arrow buttons next to the Today button or by selecting the respective calendar week in the date listbox you can scroll to other weeks.
  • This enables you to post actual hours to tasks which are not planned for the current week but which were planned for previous weeks.
  • If an invoicing key date has been set, you can scroll back beyond this day. A recording of hours before the Invoicing key date, however, is not possible. If an employee attempts to record hours before the invoicing key date anyway, the Recording not possible: Date is earlier than key date. message will be displayed.


Record Hours Worked on Further Projects/Tasks

Procedure

  • Click on the Add further projects/tasks for time recording button
    button.
    • The Add Projects and Tasks for Time Recording dialog module will be opened.
    • Select the required project and the required task from the corresponding listboxes and click on the Apply button.
      • The selected project and the selected task will be inserted in the respective group of the Time Recording module. The recording of hours worked can be done as described above.

Record Future Hours Worked (Vacation, Sickness, etc.)

Information

  • The existence of projects for which the the recording of future hours worked is permitted (in practice, these are mostly overhead cost projects) and the existence of the respective tasks (e.g. vacation) are a prerequisite for the recording of future hours.

Procedure

  • Move to the week for which you want to record overhead costs by clicking on the arrow buttons.
  • In the Time recording also for future hours worked group, overhead cost projects are displayed with the corresponding tasks in which the resource of the logged-on user is planned.
  • The procedure for creating hours is equal to the procedure in the "Record Hours Worked to Projects/Tasks in Which One is Planned".

Note

  • If the resource of the employee is not directly planned in an overhead project but has permission to record time in this overhead project, the project is not immediately listed in the Time recording also for future hours group, but it must first be inserted in the time recording module via the Add Projects and Tasks for Time Recording module. For more information, see the "Hours Worked on Further Projects/ Tasks" section.

Send Forecasts of Remaining Effort

Information

  • In case an employee notices upon completion of a task planned for him/her that the effort is higher than planned, he/she has the option to report them to the project manager responsible in the form of a remaining effort forecast.

Procedure

  • Click on the Send forecast
    button in the header area of the Time Recording module.
  • The Send Forecast module will be opened.
  • Enter the estimated remaining effort in the Forecast field in the line of the required task and save.
  • Click the Send forecast
    button in the project line.
  • The Send Info module is opened, containing an automatically created message.
  • The message contains the following data: sender, actual values of the current week, remaining and forecast values as well as the expected completion date, in case it is filled.
    • The project manager of the project is automatically entered as the recipient.
  • Click on the Send button. The message is automatically sent to the recipient via e-mail.
    • Please take note of the requirements for e-mail dispatch in PLANTA project described in the topic of the Send Info module.

Note

  • If in your system the "Adaptive Cards" function is activated and configured, the Send Info module is not opened after clicking on the
    button but instead, an Adaptive Card with your forecast will be sent to the project manager via e-mail.

Delete/Change Recorded Hours Worked (Reverse Postings)

Procedure

  • Either rectify the required hour values directly below the time scale or delete them entirely.

Notes

  • If a particular entry cannot be deleted or changed, this may be because another posting has already been transmitted to another system for accounting or that it has been exported to another system, etc., and that in your system the automatic reverse postings function, which is active by default, is completely deactivated or deactivated for particular cases.
  • In such a case you have to cancel the concerned postings manually and make a new posting (reverse posting).

Mark Assigned Work as "Completed"

Information

  • You can mark tasks in which you are planned as "completed”.
  • To do so, activate the Completed checkbox in the line of the required task.
  • If the checkbox is activated, the actual end date will be set for the own planning in the task in question (the task itself does not have to be finished if other resources are still working on it) and
    • the task will either disappear from the display in the module after it has been refreshed
    • or it will be moved to the Non-postable objects (selected week)

Note

  • If you set the own planning for a particular task to Completed while there is still remaining effort, the remaining effort will be deleted in the next calculation of the schedule.

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.