Introduction
-
Planning → Projects panel → Click on the ID of the required project → Project panel → Agile
Information
-
In this module all agile activities are created for existing project tasks, and the already existing agile views are opened and managed.
-
When clicking on a task with agile activities, it is opened in a separate agile view.
-
There, the agile activities for this task can be viewed or edited.
-
The Agile module is only available, if the value “hybrid” is chosen for the planning method parameter in the Project Core Data module.
Create Agile Activities
Procedure
-
Click on the New Activity button in the action bar to create a new agile activity as a part of a task.
-
In the opened dialog box, choose the required task from the Task list box.
-
Enter the activity title in the Title field.
-
Save.
Note
-
In existing agile views, a new activity can also be created using the plus button at the top area or the Add Task button at the bottom area of a list.
Details
-
The task with the agile activity opens in a separate agile view.
-
Initially, the new agile activity opens automatically.
-
New agile activities are assigned the status "Pending" by default and are automatically displayed in the list of the same name.
-
The agile modification of this activity (and consequently this task) takes place in this view.
-
The agile view carries the title of the associated task.
-
Users without modification rights can only select tasks in the Task listbox to which they are assigned as a resource,.
Create Agile Activities in the Schedule
Procedure
-
Position the cursor on the record of the required task.
-
Open the context menu by clicking the Quick Access button.
-
In the context menu, choose the Create Activity option.
Agile Editing of an Activity/a Task.
Information
-
Tasks with agile activities are displayed and edited in a separate agile view.
Details
-
A newly created agile view is displayed in Kanban form by default.
-
The View button in the action bar can be used to switch between three display forms of the view:
-
Kanban view
-
Calendar view
-
Activities must be given a start and/or due date to be displayed in this display form.
-
-
Tabular view
-
-
By clicking the
Show/Hide Sidebar button in the action bar, a sidebar is displayed. There,
-
the resources assigned to the task are displayed together with their respective project role,
-
user-defined fields and labels for detail views are created, displayed, and managed,
-
available actions (e. g. Delete Agile View) as well as
-
a history of all events within the agile view are displayed.
-
-
The view title can be adjusted using the
Edit View Title button in the action bar.
-
New agile activities initially are assigned the status "Pending" and are automatically displayed in the list of the same name.
-
Custom statuses can be created in the project settings.
-
All agile views a user is authorized to access, are displayed project-wide in the My Agile Views module.
Detail View for Agile Views
Information
-
Within an agile view, activities are displayed individually, independent from the display form of the view.
-
The status of an activity always corresponds to the list in which that activity is displayed.
-
Activities are moved back and forth between the lists using drag and drop.
-
The status of an activity is automatically adjusted when it is moved.
-
-
By clicking on an activity the detail view is opened.
-
The activity is edited in the detail view.
-
-
Activities that are marked as “Completed” in the detail view are grayed out.
Details
-
In the detail view for an agile activity, you can
-
assign members and labels,
-
set the start and due date,
-
add a description of the activity,
-
fill in user-defined fields, and
-
create checklists.
-
-
The following tabs are available in the bottom area of the detail view:
-
Under the Feed tab, the history of all events within the individual Activity is displayed.
-
Under the Comments tab, comments are written and viewed.
-
When assigning members, only resources that are assigned to the task are offered. Users with modification rights can additionally choose more users. These are automatically assigned to the task as a resource.
Delete Agile View
Procedure
-
Unhide the sidebar by clicking on the
Show/Hide Sidebar button in the action bar.
-
Open the Actions section.
-
Click on the Delete Agile View button.
-
Views with existing activities cannot be deleted.
-
Authorizations
Information
-
Rights in the Agile module are based on the logged-in user's rights in the respective project. There are no separate memberships for agile views or activities.
-
Three user groups are distinguished:
-
Users With Modification Rights: Multi-project manager, project manager and stakeholder with modification rights for the project.
-
Task Resources: Users who are assigned to the respective task as a resource.
-
Other Users: Users who may view the project but not modify it.
-
Details
|
Action |
Users With Modification Rights |
Task Resource |
Other Users |
|---|---|---|---|
|
View Agile Views and Activities |
X |
X |
X |
|
View Project Settings |
X |
X |
X |
|
Edit Project Settings |
X |
– |
– |
|
Create Agile Activities and Views |
X |
only for assigned tasks |
– |
|
Edit and Delete Agile Activities and Tasks |
X |
only for assigned tasks |
– |
|
Assign Assigned Resources as Members |
X |
X |
– |
|
Assign More Users as Members |
X |
– |
– |
Agile activities from tasks to which the user is not assigned are displayed as output fields and cannot be edited.
Project Settings
Information
-
The project settings are opened in a separate view and managed, by clicking on the button with the same name in the action bar.
-
In the project settings, statuses, labels, and user-defined fields are created and managed.
-
The project settings can be viewed by all users that are authorized to view the project.
-
They can only be edited by users with modification rights.
-
Status
Details
-
Statuses in the agile view are displayed in list form.
-
The default statuses are "Pending", "In Progress", and "Completed".
-
-
Different field types are used for the user-defined fields, e.g. text, number, URL, or dropdown.
-
Only user-defined fields with the Active checkbox selected are also displayed in the Activity detail views.
-