Load per Month MOD009E3D

Introduction

  • Ressources → Utilization panel → Load per month

Information

  • In this module, the load of a resources per month is displayed below the time scale.

    • If you have selected a department resource, the loads of the corresponding person resources will be displayed as well.

  • By expanding the tree structure on the projects you can have individual tasks displayed.

  • The Remaining load of the selected resource is displayed at all levels.

Module Variants

With actual loads

By selecting this module variant, Actual load values will be displayed below the remaining load values at all levels area in the Time Scale.

Note

  • Tasks for which the resource in question is planned and which already have an Actual end will be displayed grayed out.