Introduction
-
Ressources → Utilization panel → Load per month
Information
-
In this module, the load of a resources per month is displayed below the time scale.
-
If you have selected a department resource, the loads of the corresponding person resources will be displayed as well.
-
-
By expanding the tree structure on the projects you can have individual tasks displayed.
-
The Remaining load of the selected resource is displayed at all levels.
Module Variants
|
With actual loads |
By selecting this module variant, Actual load values will be displayed below the remaining load values at all levels area in the Time Scale. |
Note
-
Tasks for which the resource in question is planned and which already have an Actual end will be displayed grayed out.