List (Project) MOD009E15

Introduction

  • Planning → Projects panel → List (Projects)

Information

  • This module provides an overview of all existing projects, providing the following information per project:

    • the project estimate recorded manually by the project manager (entire estimate) as well as estimates for individual factors (costs, effort, dates, quality, risks and opportunities, project insights) are visualized by a thumb symbol.

    • the project status calculated by the program for the cost, effort, and date factors is visualized by a respective traffic light.

    • relevant project information such as project priority, project manager, and current phase of the process model, provided that a process model has been selected.

  • The estimates and statuses are displayed for the following planning statuses:

    • current planning,

    • baseline report,

    • active released status report (last released status report)

    • released status report (the status report which was active before the current one).

  • From within this module, you can create new projects using the action bar (New Project button).

Notes

  • The status report data is only displayed if respective status reports exist.

  • If there are structured projects among the displayed projects as well, only their main projects will be displayed.

Details

  • The projects displayed in this module are grouped by code. However, it is possible to change the grouping or to have the projects displayed ungrouped.

    • In the Group by field you can either change the grouping criterion by making a selection from the listbox, or delete it. After you have clicked on the Apply changes button, the projects are either displayed grouped by the selected criterion or they are displayed ungrouped.

      • If you change the grouping criterion in another module of the panel which also contains grouping criteria, it automatically takes effect in the current module as well.

  • The projects to be displayed in this module can be filtered using object filters.

    • If there already is an object filter, it can be selected from the listbox on the Filter field. After clicking on the Apply changes button, only projects which correspond to the filter are displayed.

    • You can edit existing object filters or create new ones in the Object Filter module which is opened via the Edit filter button.

    • If an object filter is selected in one of the modules which use object filters, it automatically takes effect in all other modules with object filters as well.

  • Clicking on the ID of the required project (planning object) switches to the corresponding panel where the project's (planning object's) data can be edited or viewed, depending on the user rights.

Only users with multi-project manager, multi-portfolio manager, or multi project/request manager rights can create new projects from this module.

  • By clicking on the report number you switch to the Status Report module.

Module Variants

Base

In this variant, the estimate values and the values calculated by the program are displayed for different factors like costs, effort, dates, etc.

Trend Analysis

In addition, trend values which show the development in comparison with

  • the baseline report on one hand

  • the active status report on the other hand.