Introduction
-
Planning → Programs panel → Click on the ID of the required program → Program panel → Schedule (Gantt)
For information
-
In this module you can
-
create and edit program tasks (in graphically or in table form)
-
connect program tasks via links
-
see tasks and milestones of the corresponding projects
-
connect tasks of the corresponding projects in table form via links
-
connect tasks (master milestones) of the program and of the assigned projects graphically or in table form via links
-
Caution
-
All newly created tasks of a program are master milestones by default.
-
Resource planning is not possible in the program schedules.
Module Variants
|
Base |
Tasks are displayed with the assigned links. New program tasks and links can be created and edited for both programs and projects. |
|
|
A variant of the Schedule optimized for printing is displayed. |
|
Quality Gates |
Displays the quality gates predefined by the portfolio manager and their activities to be completed. |
Create Schedule
Information
-
The schedule of a program is automatically created when you create individual tasks which are milestones at the same time.
Procedure
-
Insert an empty task row, e.g., by clicking the New Task button in the action bar or the green plus icon directly below it.
-
Enter a task name in the Task name field.
-
Create further tasks in the same way.
-
Save and click on the
Generate WBS code button. As a result, an ID will automatically be generated for the new task in the Task field. In PLANTA standard, the WBS codes are used as task IDs in schedules.
Tasks in PLANTA project have two IDs:
-
A technical task ID is automatically created. It is an incrementing task number which is usually invisible in user modules in the PLANTA standard system.
-
A functional task ID is either generated automatically or allocated manually.
-
Via the global Use WBS code instead of ID parameter you can define which of these three variants will be used as functional ID. The chosen functional ID then applies system-wide to all user modules in which tasks are displayed.
-
Tasks (Master Milestones)
Information
-
All newly created tasks of a program are master milestones by default.
Edit task
Information
-
By entering or changing the task parameters in the required fields of the Task module the individual tasks of a program schedule can be edited.
Terminate Task
Procedure
-
Enter Requested start and Requested end in the respective fields or define the Remaining duration.
-
Click on the Calculate schedule button in the action bar. In doing so, calculated dates of the task (Calc. start and Calc. end) are calculated automatically.
-
If you do not define any requested dates for tasks but only durations, the Requested start of the project will be used as start date for the calculation. If you have not defined any requested dates for the project either, the tasks will be defined from today’s date on.
-
Change Note/Estimate Flag
The note or the estimation of a program task (master milestone) can be changed in the Task module.
Read Out Task Chain
Procedure
-
Right-click on the required task.
-
Select the Show predecessor/successor context menu command.
-
The What do you want to do? dialog message is displayed with selection options (via the buttons) for the display of the data in the Task Chain module.
-
Depending on the selection made in the dialog module, the following is displayed in the Task Chain module:
-
direct predecessors or direct successors of the selected task or
-
all predecessors or all successors of the selected task or
-
all predecessors and successors of the selected task (i.e. the entire network).
-
-
Finish Task
Procedure
-
Enter the required end date in the Actual end data field in the line of the required task.
-
Save and recalculate the schedule.
Links
Links map dependencies between tasks of in a project and have an impact on the calculation of the project dates. For information on the options for mapping dependencies between projects, please click here.
Internal and External Links
Information
-
Internal links in a program schedule are links between individual tasks (master milestones) at program level.
-
External links in a program schedule are links from the program's tasks to the tasks of the assigned projects and vice versa, or from the tasks of an assigned project to the tasks of another assigned project.
External Tasks
Information
-
External tasks are tasks of another project/program which can be displayed in the schedule of the selected program in order to visualize the dependencies between the program and other projects.
Quality Gates
Information
-
Quality Gates are a type of controlling element of the portfolio manager for monitoring the progress of the planning objects contained in the portfolio.
-
Quality gates are defined by the portfolio manager, scheduled and assigned to the individual planning objects.
-
Project managers or program managers can see the assigned quality gates in the Schedule in the Quality Gates module variant of the corresponding planning object and record the probable date of completion of the quality gates and therefore enable the portfolio manager to monitor the compliance with the specifications.
Edit Quality Gates
-
Enter the estimated date for the completion of the quality gate in the Prob. completed on field.
-
In the % completed field, enter or update the degree of completion of of the quality gate.
-
Note: the Actual end field is filled by the project manager by setting the Approval in the Quality Gates module.
-
Since, from a technical point of view, quality gates are tasks, the requested end calculated for them can influence the project dates. As quality gates are automatically transferred to the planning object when the planning object is assigned to the portfolio, you may have to check the schedules of the planning objects or the dates of the quality gates after assigning the planning objects to portfolios.