Change Requests MOD009E6G

Introduction

  • Planning → Portfolios panel → Click on the ID of the required portfolio → Portfolio panel → Change Requests

Alternative Introduction

Alternative Introduction

  • There are several ways to access the desired planning object or portfolio panel and its associated modules:

    • via Quick Access in the user menu (My Objects and Favorites)

    • via the Global Search function in the user menu (Direct Entry)

    • via links on planning objects or portfolios in various modules


Information

  • The Change Requests module provides an overview of the change requests of the planning objects assigned to the portfolio, grouped by

    • planning objects and within the planning objects

      • pending change requests

        • change requests which have not yet been decided on.

      • completed change requests

        • change requests which have either been approved or rejected.