Utilization of MOD009DA4

Introduction

  • Project panel → Schedule → Click on the MeineAnfragen.png button to open the Resource Requests module → Click on the Auslastung.png button on a request

  • Resource Management → Department Planning → Department Board panel → My Resource Requests → Click on the Auslastung.png button on a request

  • Multi-Project Management → Project Planning → Multi-Project Board panel → Resource Request → Click on the Auslastung.png button on a request

Note


Information

  • In this module a simulation of the utilization of the selected resource will be displayed.

  • In this utilization, the value which has been entered and saved in the My Resource Requests for the respective resource in the Approved field will be considered as well.

    • If the value is changed and you save again, the display will be refreshed accordingly.

  • Project manager and department manager are thus provided with an option to simulate the impact of requests and approvals upfront.

Details

Note

  • No capacity adjustment will be carried out. Overloads and other impact which may be caused by requests and approvals will not be indicated.

See also : Information on Resource Requests/Approvals