Introduction
-
-
Planning→ Projects (Programs) panel → Click on the ID of the required project (program) → Project (Program) panel → Status → Click on the Configure Trend Analysis button in the Status Reports area → Configure Trend Analysis
-
Planning → Projects panel → Click on the ID of the required project → Project panel → Infoboard → Click on the Configure Trend Analysis button in the action bar → Configure Trend Analysis
Information
-
This module is a dialog module.
-
In this module you have the option to select the status reports which are to be used for different trend analyses (modules see under Details) or for a comparison of the planning states.
Procedure
-
For status reports that you want to be
-
taken into account in the cost, effort, risk, and opportunity analysis, activate the Cost trend analysis checkbox.
-
taken into account in the milestone or master milestone trend analysis, activate the Milestone Trend Analysis checkbox.
-
compared with the latest status in the Deviations module, activate the Milestone Trend Analysis checkbox.
-
Note
-
If the selected project is a structured project, the checkboxes must be activated for the required report at all project levels (in the main project and in all subprojects).
Details
-
Costs, effort, risk, and opportunity data can be found in the following modules:
-
The respective graphical analysis can also be found in the above mentioned modules as well as additionally in the Info Board, Cost Reports, and Effort Reports modules.
-
Milestone or master milestone trend analysis data can be found
-
in the Schedule module in the Milestone Trend and Master Milestone Trend module variants.
-
The respective graphical analysis can be found in the Info Board module.
-
|
See also: Status Report, Program Status Report |